Sunrise Valley Dam Enlargement
Project Info
Client: Freestyle Hops Limited
Project Description
This was an exciting prospect for us and we took up the challenge. In total we managed to excavate 49,233m3, stripped and re-spread 10,500m3 of topsoil and installed 120Lm of subsoils.
There were a few construction challenges involved in this project which included working in wet conditions, water springs within the work site constantly running, removing fill from the dam with limited solid ground to run machines over and creating haul roads from soft fill material. Our team showed innovation by mixing the limited amount of hard fill at the bottom of the pond with the soft fill, to create stronger haul roads.
With streams near to the work site, environmental controls were also important. These ensured there was no contamination from machine refueling and sediment discharge was correctly managed.
Once the dam was complete in June 2016, we were lucky enough to have some large storm events, which filled the dam nicely for the summer.
Related Projects
August 2022 Flood Recovery
August 2022 Flood Recovery Project Info Clients: Fulton Hogan/Waka Kotahi (NZTA)/Nelson City Council Project Description In response to the extraordinary weather in August 2022 which saw extensive rainfall, flooding and slips across the region, Taylors deployed...
Seafield Terrace Rock Revetment
Seafield Terrace Rock Revetment WorksProject InfoClient: Nelson City CouncilProject DescriptionWINNER: CCNZ Nelson Marlborough 2021 Awards, $750,001 – $1.5 million Category This project entailed coastal erosion remedial work at Seafield Terrace, Glenduan. After a...
Pigeon Valley Fire
Pigeon Valley FireProject InfoClient: FENZ National Incident TeamProject Description2019 CCNZ Nelson Marlborough Award Winner. $700,001 – $1.5 million category, sponsored by Land Dimensions Ltd We were very honored to win the above award for our work assisting on the...